That’s a very important question 👍 — because payment schedules vary a lot between independent designers, boutique firms, and turnkey companies in Delhi NCR. Having this clear in writing avoids cash-flow stress and disputes later.
✅ Typical Payment Schedules in Interior Design
🔹 1. Independent Designers (Design-Only Services)
- 30–40% advance → to start design work (layouts, mood boards, 3Ds).
- 30–40% mid → before detailed drawings & BOQ handover.
- 20–30% final → on submission of complete design package.
👉 Clear for small scope or design-only projects.
🔹 2. Boutique Design + Execution Firms
- 10–15% booking/advance → to lock designer & prepare concepts.
- 30–40% after design approval → when carpentry / factory orders are placed.
- 30–40% mid-stage → during execution (woodwork, civil, painting).
- 10–20% final → after site handover, snag corrections, or furnishing stage.
👉 Usually milestone-based (kitchen started, wardrobes ready, false ceiling complete, etc.).
🔹 3. Large Turnkey Companies (Livspace, HomeLane, etc.)
- 10% token booking → to start design.
- 40% after final design sign-off → for ordering materials.
- 40% before production/dispatch → major factory build.
- 10% final → at installation/handover.
👉 More rigid, but standardised.
✅ What You Should Ask Your Designer
- How much advance do you need to start?
- Is payment linked to milestones (design approval, factory order, carpentry stage) or only fixed dates?
- Do you provide receipts & GST invoices for each stage?
- Can we keep a retention amount (5–10%) until final handover?
- Do you allow instalment plans for large projects?
⚠️ Red Flags
- Asking 50–70% upfront 🚩 before showing drawings/3Ds.
- Only time-based schedule (dates) instead of milestone-based.
- No receipts or invoices for payments.
- Designer resists holding final 10% till handover.
✅ Pro Tip
- A safe schedule = 10–15% advance, 70–75% milestone-based payments, 10–15% retention till handover.
- For kitchens/wardrobes → expect 40–50% payment at factory order stage (since custom work starts).
- Always link payments to progress milestones, not just calendar dates.