That’s one of the most important questions to ask an interior designer 📝 — because delays and last-minute changes are very common in home interiors, especially in Delhi NCR where labour availability, material delivery, and festival seasons all affect timelines.
Here’s what you should expect in a professional answer and how a good designer should handle it:
✅ How a Good Designer Handles Delays
- Clear Timeline with Milestones
- They should give you a written schedule (design stage, carpentry, civil, electrical, painting, installation).
- Each stage has start and finish dates.
- Regular Updates
- Weekly progress reports (photos, site visits).
- Early warnings if material delivery or labour shortage might delay things.
- Contingency Buffer
- Most good firms include a buffer of 10–15% extra time in the timeline.
- Example: if project is 10 weeks, they may officially quote 11–12 weeks.
- Penalty / Compensation Clause
- Some turnkey firms agree to penalties for excessive delays beyond agreed buffer (e.g., ₹500–₹1000/day after deadline).
- Not all agree, but you should ask.
🔄 How They Handle Last-Minute Design Changes
- Change Request Process
- They should have a formal system: you request → they issue revised drawing/3D + cost/time impact → you approve → they implement.
- Prevents confusion on site.
- Cost Impact Transparency
- Last-minute changes usually mean extra cost (material wastage, new labour).
- A professional designer quotes the cost impact upfront before starting changes.
- Time Impact Communication
- Even a small change (e.g., different laminate) can delay work if stock isn’t available.
- They should tell you how many days the change will add.
- Limitations
- Major changes (like shifting walls, moving kitchen after plumbing done) can be very costly and delay weeks. A good designer explains when a change is too late or impractical.
⚠️ Red Flags
- Designer says “don’t worry, we’ll adjust” but doesn’t share written revised timelines/costs.
- No process for recording changes → leads to disputes later.
- Blames labour/vendors for all delays but doesn’t take ownership.
💡 Pro Tip for You
When signing a contract, add a clause for:
- Timeline buffer (e.g., 12 weeks + 2 weeks grace).
- Change order process (all changes must be written + signed with revised cost/time).
- Delay accountability (clear reasons that are chargeable vs excusable, like unavoidable government restrictions).
👉 Would you like me to draft a sample “delay & change clause” that you can add to your interior design agreement, so you’re legally protected in case of overruns?