Great question 👍 — because timeline clarity is just as important as budget. For a 2BHK home in Delhi NCR, the timeline depends on:
- Scope of work (basic vs full interiors).
- Material choices (factory-made modular vs on-site carpentry).
- Designer type (freelancer vs turnkey firm).
âś… Typical Timelines for a 2BHK Interior
1. Basic Interiors (Essentials Only)
- Includes: modular kitchen, wardrobes, basic false ceiling, painting.
- Timeline: 6–8 weeks (1.5–2 months).
- Best if you’re doing only functional work with minimal décor.
2. Mid-Range Full Interiors
- Includes: modular kitchen, wardrobes, false ceiling, electrical, painting, some furniture & décor.
- Timeline: 10–14 weeks (2.5–3.5 months).
- Most common for Delhi NCR 2BHK apartments.
3. Premium / Luxury Interiors
- Includes: high-end finishes, bespoke furniture, stone/marble work, automation, full décor styling.
- Timeline: 16–20 weeks (4–5 months).
- More common in larger apartments / builder floors.
🔑 Factors That Can Affect Timelines
- Material delays → imported laminates, lights, Italian marble can add 2–3 weeks.
- Design indecision → if you take long to approve laminates/tiles.
- On-site carpentry vs modular factory → factory-made is faster, but approvals must be locked early.
- Labour availability → festive seasons & monsoons can slow work.
⚠️ Red Flags
- Designer promises “done in 30 days” → 🚩 usually unrealistic for a proper 2BHK.
- No written milestone chart → you’ll have no way to track if it’s slipping.
âś… Pro Tip
For a standard 2BHK in Delhi NCR:
- Plan for 10–14 weeks as realistic.
- Add buffer of 2 weeks for unexpected issues.
- Always get a milestone-based schedule in writing (design → civil → electrical → carpentry → finishing).
👉 Would you like me to create a sample 2BHK interior timeline (Excel / Gantt chart) with stage-wise milestones (kitchen, wardrobes, false ceiling, painting, décor), so you can hand it to your designer and lock timelines?