Do you provide a milestone-based project schedule?

That’s an excellent question 👍 — because a milestone-based project schedule is the backbone of a smooth interior project. Without it, everything becomes vague and delays pile up.

Here’s how a good designer in Delhi NCR should handle it:


✅ What a Milestone-Based Schedule Looks Like

1. Design Stage (2–4 weeks)

  • Site measurement & concept layouts → 1 week
  • Mood boards & 3D renders → 1–2 weeks
  • BOQ (Bill of Quantities) & final approvals → 1 week

2. Execution Stage (8–12 weeks for 2BHK/3BHK)

MilestoneScope of WorkTime (Approx.)
M1: Civil & DemolitionBreaking walls, basic masonry, waterproofing1–2 weeks
M2: Electrical & Plumbing Rough-inWiring, piping, AC points1–2 weeks
M3: False Ceiling & Partition WorkGypsum/POP ceiling, lighting cutouts1–2 weeks
M4: Carpentry Stage-1 (Carcass)Wardrobe carcass, kitchen base modules2–3 weeks
M5: Carpentry Stage-2 (Shutters & Finishes)Laminate/veneer/acrylic shutters, polishing2–3 weeks
M6: Painting & Wall FinishesPrimer, emulsion, wallpapers1–2 weeks
M7: Modular InstallationsKitchen, wardrobes, furniture, hardware1–2 weeks
M8: Loose Furniture & DécorSofa, dining, beds, curtains, lights1–2 weeks
M9: Snagging & HandoverFinal checks, touch-ups, cleaning1 week

👉 Total (Design + Execution) = 12–16 weeks (3–4 months) for a typical 2BHK/3BHK flat.
👉 Villas/bungalows → may take 6–8 months, depending on scale.


💡 What You Should Ask

  1. Will you give me a written milestone-based schedule?
  2. Do you provide a Gantt chart (visual timeline)?
  3. How will you track progress — weekly updates, WhatsApp photos, site visits?
  4. What’s the buffer time for unexpected delays?
  5. If a milestone slips, how will you reallocate labour to catch up?

⚠️ Red Flags

  • Designer only says: “3–4 months total” → vague, no breakdown.
  • No written timeline → you can’t hold them accountable.
  • They rely only on contractors, no project management.

✅ Pro Tip

Insist on:

  • Milestone-based schedule in writing.
  • Payment tied to milestones (e.g., “30% on carpentry completion” not “30% after 1 month”).
  • Weekly reporting against this schedule.

👉 Would you like me to create a sample milestone schedule (in Excel / Gantt chart format) that you can hand to any designer, so they commit to exact timelines stage by stage?